Town of Chatham Collection System Construction Project
Welcome Areas of Work Public Notices Schedule Information Contact
Links
Town of Chatham Website
Frequently Asked Questions (FAQ)
Comprehensive Management Plan
Chatham Water & Sewer
Chatham DPW
Chatham Natural Resources
Town of Chatham Website
Chatham Maps Online
Chatham Businesses
Schedule

Last updated on:  

During construction this page will provide estimated dates of construction (these will be updated periodically – locations are approximate based on nearest cross street).

- Town has several Projects Planned:

  • Phase 1C-2 (Under Construction)
  • Main Street Sewer Reconstruction Project - in Design (anticipated Construction TBD)
  • Remainder of Phase 1C - in Design (Construction TBD)
  • Phase 1D - Harwich Connection and Route 137 / Morton Road Area - in Design (Construction TBD)

For some businesses within the Construction Area: Please visit our listing of Chatham Businesses for more information on their location and hours of operation. Requests to add a Chatham business can be sent to the Town or the Project Manager listed on our Contacts Page.

 

2017-2018

SEWER CONSTRUCTION

 



 

FALL/WINTER 2017 - WINTER 2018

Please see the map showing active construction, detours and alternate routes, see map and link below):

Construction:
Start Fall 2017 - Sewer Construction (Weather Permitting)

CONSTRUCTION ACTIVITY - CONTRACT 1C-2 IS CURRENTLY UNDER CONSTRUCTION.  CONSTRUCTION STARTED ON December 18, 2017 and shall continue through May 2018.

ONCE CONSTRUCTION BEGINS:

Construction dates are subject to change depending on construction progress and weather conditions.  Construction is anticipated to continue through the winter construction season.  See Public Notices page for Town issued Press Releases and additional information.

Contractor hours are typically from 7:00 AM to 5:00 PM, weather depending. No work is scheduled for nights, weekends, or holidays.  Work may be extended to 7 PM under special circumstances.


When roads/construction areas/zones are closed to thru-traffic, the road will be open to Local Business Traffic and Residents unless otherwise noted.  Please follow construction signs as access to/from local businesses and side streets within the construction zones will be construction-dependent and may change during the course of the day or work week.  Work may continue in these areas even if not shown in red, and may be performed using alternating traffic.


Click on a Construction Area on the map below to get related road and construction schedule information.

CONTRACT 1C-2 AREA

Construction Area 1 (Janes Way and Earles Way)

 
PAVING ACTIVITIES TO COMMENCE BETWEEN OCTOBER 22 AND NOVEMBER 2

 

Crews will return to perform final paving on these roads after completion of paving on Absegami Run, Oyster Bluff, Oyster Pond Furlong, Wheldon Way, and The Cornfield. Roads will be passable at the end of every day, though residential access may be limited during the day.

 

Construction Area 2 (Wheldon Way)

 
PAVING ACTIVITIES TO COMMENCE BETWEEN OCTOBER 22 AND NOVEMBER 2

 

Crews will return to perform final paving on this road beginning on Tuesday October 23. Roads will be passable at the end of every day, though residential access may be limited during the day.

 

Construction Area 3 (The Cornfield)   

 
PAVING ACTIVITIES TO COMMENCE BETWEEN OCTOBER 22 AND NOVEMBER 2

 

Crews will return to perform final paving on this road beginning on Tuesday October 23. Roads will be passable at the end of every day, though residential access may be limited during the day.

Construction Area 4 (Village Landing)

 
PAVING ACTIVITIES TO COMMENCE BETWEEN OCTOBER 22 AND NOVEMBER 2


Crews will return to perform final paving on this road; it is anticpated to begin on October 22 and November 2. Roads will be passable at the end of every day, though residential access may be limited during the day.


Construction Area 5 (Oyster Bluff and Absegami Run)  
PAVING ACTIVITIES TO COMMENCE BETWEEN OCTOBER 22 AND NOVEMBER 2

 

Crews will return to perform final paving on after completion of Wheldon Way and The Cornfield. Roads will be passable at the end of every day, though residential access may be limited during the day.

 

Construction Area 6 (Spinnaker Lane)

 
PAVING ACTIVITIES TO COMMENCE BETWEEN OCTOBER 22 AND NOVEMBER 2


Crews will return to perform final paving on this road after completion of paving on Village Landing. Roads will be passable at the end of every day, though residential access may be limited during the day.

Construction Area 7 (Tabitha Terrace)

 
NO ACTIVE DETOURS
 Crews will return at a later date to complete site restoration.

Construction Area 8 (Oyster Pond Lane)

 
PAVING ACTIVITIES TO COMMENCE BETWEEN OCTOBER 22 AND NOVEMBER 2


Crews will return to perform final paving on this road after completion of paving on Absegami Run, Oyster Bluff, Oyster Pond Furlong, Wheldon Way, The Cornfield, Earle's and Jane's Way.
Roads will be passable at the end of every day, though residential access may be limited during the day.



Construction Area 9 (Oyster Pond Furlong and Town Landing)

 

PAVING ACTIVITIES TO COMMENCE BETWEEN OCTOBER 22 AND NOVEMBER 2


Crews will return to perform final paving on this road after completion of paving on Absegami Run and Oyster Bluff. Roads will be passable at the end of every day, though residential access may be limited during the day.


Construction Area 10 (Independence Lane)

 
PAVING ACTIVITIES TO COMMENCE BETWEEN OCTOBER 22 AND NOVEMBER 2


Crews will return to perform final paving on this road after completion of paving on Village Landing and Spinnaker Lane. Roads will be passable at the end of every day, though residential access may be limited during the day.

 

Construction Area 11 (Inlet Road)

 
PAVING ACTIVITIES TO COMMENCE BETWEEN OCTOBER 22 AND NOVEMBER 2


Crews will return to perform final paving on this road after completion of paving on Village Landing, Spinnaker Lane, and Independence Lane. Roads will be passable at the end of every day, though residential access may be limited during the day.

 

Construction Area 12 (Shattuck Place, Shattuck Lane, Grist Mill Lane, Tide Mill Lane, Wineberry Way)

 
PAVING ACTIVITIES TO COMMENCE BETWEEN OCTOBER 22 AND NOVEMBER 2


Crews will return to perform final paving on this road after completion of paving on Absegami Run, Oyster Bluff, Oyster Pond Furlong, Wheldon Way, The Cornfield, Jane's and Earle's Way, and Oyster Pond Lane.
Roads will be passable at the end of every day, though residential access may be limited during the day.

 

 


 