Town of Chatham Collection System Construction Project
Welcome Areas of Work Public Notices Schedule Information Contact
Links
Town of Chatham Website
Frequently Asked Questions (FAQ)
Comprehensive Management Plan
Chatham Water & Sewer
Chatham DPW
Chatham Natural Resources
Town of Chatham Website
Chatham Maps Online
Chatham Businesses
Schedule

Last updated on:  

During construction this page will provide estimated dates of construction (these will be updated periodically – locations are approximate based on nearest cross street).

- Town has several Projects Planned:

  • Phase 1C-2 (Under Construction)
  • Main Street Sewer Reconstruction Project - in Design (anticipated Construction TBD)
  • Remainer of Phase 1C - in Design (Construction TBD)
  • Phase 1D - Harwich Connection and Route 137 / Morton Road Area - in Design (Construction TBD)

For some businesses within the Construction Area: Please visit our listing of Chatham Businesses for more information on their location and hours of operation. Requests to add a Chatham business can be sent to the Town or the Project Manager listed on our Contacts Page.

 

2017-2018

SEWER CONSTRUCTION

 



 

FALL/WINTER 2017 - WINTER 2018

Please see the map showing active construction, detours and alternate routes, see map and link below):

Construction:
Start Fall 2017 - Sewer Construction (Weather Permitting)

CONSTRUCTION ACTIVITY - CONTRACT 1C-2 IS CURRENTLY UNDER CONSTRUCTION.  CONSTRUCTION STARTED ON December 18, 2017 and shall continue through May 2018.

ONCE CONSTRUCTION BEGINS:

Construction dates are subject to change depending on construction progress and weather conditions.  Construction is anticipated to continue through the winter construction season.  See Public Notices page for Town issued Press Releases and additional information.

Contractor hours are typically from 7:00 AM to 5:00 PM, weather depending. No work is scheduled for nights, weekends, or holidays.  Work may be extended to 7 PM under special circumstances.


When roads/construction areas/zones are closed to thru-traffic, the road will be open to Local Business Traffic and Residents unless otherwise noted.  Please follow construction signs as access to/from local businesses and side streets within the construction zones will be construction-dependent and may change during the course of the day or work week.  Work may continue in these areas even if not shown in red, and may be performed using alternating traffic.


Click on a Construction Area on the map below to get related road and construction schedule information.

CONTRACT 1C-2 AREA

Construction Area 1 (Janes Way and Earles Way)

 
NO ACTIVE DETOURS

 

Crews will return at a later date to complete final paving.

Construction Area 2 (Wheldon Way)

 
NO ACTIVE DETOURS

 

Crews will return at a later date to complete final paving.

 

Construction Area 3 (The Cornfield)   

 
NO ACTIVE DETOURS

 

Crews will return at a later date to complete final paving.

Construction Area 4 (Village Landing)

 
NO ACTIVE DETOURS

Crews will return at a later date to complete final paving.

Construction Area 5 (Oyster Bluff and Absegami Run)  
NO ACTIVE DETOURS

 

Crews will return at a later date to complete final paving.

 

Construction Area 6 (Spinnaker Lane)

 
NO ACTIVE DETOURS

 

Crews will return at a later date to complete final paving.

 

Construction Area 7 (Tabitha Terrace)

 
NO ACTIVE DETOURS
 Crews will return at a later date to complete sewer testing and site restoration.

Construction Area 8 (Oyster Pond Lane)

 
NO ACTIVE DETOURS


Crews will return at a later date to complete final paving
.


Construction Area 9 (Oyster Pond Furlong and Town Landing)

 

NO ACTIVE DETOURS

Crews will return at a later date to complete final paving.

Construction Area 10 (Independence Lane)

 
NO ACTIVE DETOURS

Crews will return at a later date to complete final paving.

 

 

Construction Area 11 (Inlet Road)

 
NO ACTIVE DETOURS

Crews will return at a later date to complete final paving.

 

Construction Area 12 (Shattuck Place, Shattuck Lane, Grist Mill Lane, Tide Mill Lane, Wineberry Way)

 
ACTIVE CONSTRUCTION ZONE

Crews be installing gravity sewer and water mains on Shattuck Place, Shattuck Lane, Grist Mill Lane, and Tide Mill Lane during the week of May 29, June 4, June 11, and June 18, 2018.

 

 


 
Town of Chatham  |  MassDOT Traffic