Schedule

Last updated on: July 28, 2021

During construction this page will provide estimated dates of construction (these will be updated periodically – locations are approximate based on nearest cross street). Please refer to "Areas of Work" page for street listings.

- Town has several Projects in process:

  • Phase 1C- 3 & 4: (in Construction)
  • Phase 1D-1: - Chatham/Harwich Connection - Old Queen Ann/Meetinghouse/Middle Roads (in Construction)
  • Phase 1E: Stony Hill / Crowell Road Infrastructure Project (in Construction)
  • Main Street Sewer Reconstruction Project - in Design (anticipated construction TBD)
  • Mill Pond Pumping Station Upgrade - in Design (anticipated construction TBD)
  • Phase 1C -5: Cedar Street and Pond View/Kelly Lane/ Woodcarver Knoll in Design (Construction TBD)
  • Phase 1D - 2: Route 137 / Morton Road Area - in Design (Construction TBD)

For some businesses within the Construction Area: Please visit our listing of Chatham Businesses for more information on their location and hours of operation. Requests to add a Chatham business can be sent to the Town or the Project Manager listed on our Contacts Page.

 

2019/2020

SEWER CONSTRUCTION PROJECT (LIST)

 
Active Detours Detour Map
Crowell Road Detour Detour Map

Fall 2019 - Spring 2021

Please see the map showing active construction, detours and alternate routes, see map and link below):
Sewer Construction (Weather Permitting)
Construction Contracts:

 

 

PHASE 1C-3&4: CONTRACT NO. 2018-CWMP-2 (LOCATION MAP)

 

The following roads are included in this contract:

 

Balfour Lane; Barbara Drive; Bay View Street; Captain Richards Way; Carolyn Drive; Christopher Hardings Lane; Cynthia Drive; Ell Street; Ellis Street; Ethelma Drive; Heritage Lane; Jeanette Drive; Jeanette Road; Lime Hill Road; Linden Tree Lane; Perch Pond Road; Sky Way; Smith Street; Snow Lane; Uncle Alberts Drive; Vineyard Avenue; Waveland Avenue; White Pond Road; Wilfred Road


CONSTRUCTION ACTIVITY - CONTRACT 1C-3&4 is scheduled to start September 2019 and is anticipated to continue through Spring 2021.

 

PHASE 1D-1: CONTRACT NO. 2018-CWMP-4: CHATHAM/HARWICH CONNECTION PROJECT (LOCATION MAP)

 

The following roads are included in this contract:

 

 

Old Queen Anne Road; Meetinghouse Road; Duncan Lane; Mallard Road; Partridge Path; Middle Road

 

CONSTRUCTION ACTIVITY - CONTRACT 1D-1 began in the Fall of 2019 and is anticipated to continue through Spring 2021.

 

PHASE 1E: CONTRACT NO. 2019-CWMP-3: STONY HILL/CROWELL ROAD INFRASTRUCTURE PROJECT

 

The following roads are included in this contract:

 

 

George Ryder Road South; Market Place; Hardings Lane; Crowell Road; Stony Hill Road; Lake Street

 

CONSTRUCTION ACTIVITY - Phase 1E - (Stony Hill / Crowell Road) began in the Fall 2020 and is scheduled to continue through Fall 2021.

GENERAL INFORMATION ALL CONSTRUCTION CONTRACTS (ONCE CONSTRUCTION BEGINS):

Construction dates are subject to change depending on construction progress and weather conditions.  Construction is anticipated to continue through the winter construction season.  See Public Notices page for Town issued Press Releases and additional information.

Contractor hours are typically from 7:00 AM to 5:00 PM, weather depending. No work is scheduled for nights, weekends, or holidays.  Work may be extended to 7 PM under special circumstances.


When roads/construction areas/zones are closed to thru-traffic, the road will be open to Local Business Traffic and Residents unless otherwise noted.  Please follow construction signs as access to/from local businesses and side streets within the construction zones will be construction-dependent and may change during the course of the day or work week.  Work may continue in these areas even if not shown in red, and may be performed using alternating traffic.

Click on a Construction Area on the map below to get related road and construction schedule information.

CONTRACT 1C-3&4 AREA

Click on a Construction Area on the map below to get related road and construction schedule information.

CONTRACT 1D-1 AREA

Click on a Construction Area on the map below to get related road and construction schedule information.

CONTRACT 1E - STONY HILL/CROWELL ROAD AREA

Construction Area 1 (Ethelma Drive)

Fall 2019 - Spring 2021

Sewer Construction is currently planned to begin the week of 11/18/19 and continue through 1/24/2020. Gravity sewer lateral work is planned to begin the week of 1/13/2020 and continue through the week of 1/24/2020.  Please note that watermain and services work is also expected in this area.

 

Sewer testing is planned to begin 4/13/2020 and continue through to 5/01/2020 in this area.

 

Road work is expected to begin 10/28/2020 and continue through to 11/20/2020. Road work will include lowering manhole covers and pavement preparation/installation on Ethelma, Barbara, and Carolyn Drives neighborhoods.

 

Paving planned to begin in this area on 5/03/2021.

 

Estimated Schedule includes:

Gravity sewer installation 11/2019 - 12/2019

Gravity sewer laterals 12/2019 - 1/2020

Final Paving estimated 5/2021

 

Construction Area 2 (Barbara Drive)

Fall 2019 - Spring 2021

Construction is currently planned to begin the week of 11/18/19 and continue through 1/24/2020. Gravity sewer lateral work is planned to begin the week of 1/13/2020 and continue through the week of 1/24/2020. Please note that watermain and services work is also expected in this area.

 

Sewer testing is planned to begin 4/13/2020 and continue through to 5/08/2020 in this area.

 

Road work is expected to begin 10/28/2020 and continue through to 11/20/2020. Road work will include lowering manhole covers and pavement preparation/installation on Ethelma, Barbara, and Carolyn Drives neighborhoods.

 

Paving planned to begin in this area on 5/03/2021.

 

Estimated Schedule includes:

Gravity sewer installation 11/2019 - 12/2019

Gravity sewer laterals 12/2019 - 1/2020

Final Paving estimated 5/2021

 

Construction Area 3 (Carolyn Drive)   

Fall 2019 - Spring 2021

Construction is currently planned to begin the week of 11/18/19 and continue through 12/13/19. Gravity sewer main installation and laterals is planned to resume the week of 1/20/2020 and continue through to 3/13/2020. Cleanup of this area is expected for the week of 3/09/2020 once lateral work is complete. Please note that watermain and services work is also expected in this area.

 

Sewer testing is planned to begin 4/13/2020 and continue through to 5/08/2020 in this area.

 

Road work is expected to begin 10/28/2020 and continue through to 11/20/2020. Road work will include lowering manhole covers and pavement preparation/installation on Ethelma, Barbara, and Carolyn Drives neighborhoods.

 

Paving planned to begin in this area on 5/03/2021.

 

Estimated Schedule includes:

Gravity sewer installation 11/2019 - 2/2020

Gravity sewer laterals 12/2019 - 3/2020

Final Paving estimated 5/2021

 

Construction Area 4 (Jeanette Drive & Jeanette Road)

Fall 2019 - Fall 2021

Jeanette Drive: Construction is currently planned to begin the week of 11/18/19 and continue through 12/27/19. Gravity sewer lateral work is planned to begin the week of 1/13/2020 and continue through the week of 1/24/2020.  Please note that watermain and services work is also expected in this area.

 

Sewer testing is expected to begin 05/04/2020 and continue through to 05/08/2020 in this area.

 

Road work is expected to begin 11/23/2020 and continue through to 12/11/2020. Road work will include pavement preparation on Jeanette Drive area.

 

Jeanette Road: Construction of the gravity sewer is currently planned to begin the week of 1/13/2020 and continue through the week of 1/24/2020. Please note that watermain and services work is also expected in this area.

 

Road work is expected to begin 10/28/2020 and continue through to 12/11/2020. Road work will include pavement preparation on Perch Pond Road/Jeanette Road areas.

 

Jeanette Drive/Road: Testing of the sewer main to be started the week of 2/1/2021 in this area, and continue intermittently through 2/26/2021.

 

Paving planned in the Jeanette Drive area on 5/03/2021.

 

Estimated Schedule includes:

Jeanette Drive:

Gravity sewer installation 11/2019 - 12/2019

Gravity sewer laterals 12/2019 - 1/2020

Final Paving estimated 5/2021

Jeanette Road:

Gravity sewer installation 1/2020 - 1/2020

Gravity sewer laterals 12/2019 - 2/2020

Final Paving estimated 4/2021

 

Construction Area 5 (Wilfred Road and Cynthia Drive / Wilfred Road Odor Control Site)

SITE WORK (SEE BELOW)

Fall 2019 - Spring 2021

Construction is currently planned to begin the week of 12/09/19 and continue through 1/10/2020 for low pressure sewer main and lateral installation on Wilfred Road.  Gravity Sewer Installation is planned to begin the week of 1/27/2020 and continue through to 2/28/2020; with watermain work near the intersection of Wilfred Road and Jeanette Road/Drive.

 

Work at the odor control site on Wilfred Road will occur intermittently through July 2021.

 

Paving, roadway cleanup and site restoration planned for the weeks of 5/10/2021, 5/17/2021 and 5/24/2021.

 

Staging of equipment and materials within the road right-of-way is likely for this area.

 

Road milling/pavement preparation is planned in this area beginning the week of 5/03/2021.

 

Hydroseeding planned for this area the week on 6/7/2021.

 

Estimated Schedule includes:

Test Pits 9/2019

Force main installation 10/2019

Relocate existing water main - 2/2020

Gravity sewer installation 1/2020 - 2/2020

Low pressure sewer installation 12/2019 - 2/2020

Sewer laterals 12/2019 - 02/2020

Final Paving estimated 5/2021

 

Wilfred Road Odor Control Site:

Construction 12/2020 - 7/2021

 

Construction Area 6 (Balfour Lane / Balfour Lane Pumping Station)

PUMP STATION WORK (SEE BELOW)

Fall 2019 - Spring 2021 (Roadwork) / Winter 2019 - Spring 2021 (Pumping Station Work)

Construction is planned to begin 1/29/2020 for mobilization and to begin Gravity Sewer Installation through 1/31/2020. Work is then expected to continue starting the week of 2/10/2020 through 3/20/2020 for Gravity Sewer Work, Service Laterals, and Force Main Work. Electrical work by an Eversource contractor is expected to begin the week of 9/14/2020 and last approximately 4 weeks.

 

Pump station work is estimated to begin the week of 4/27/2020 and continue intermittently through July 2021.

 

Road work is expected to begin 11/09/2020 continuing through to 11/25/2020. Road work will include lowering manhole covers and pavement preparation/installation on Balfour Lane.

 

Paving planned for this area the week of 5/17/2021.

 

Staging of equipment and materials within the road right-of-way is likely for this area.

 

Estimated Schedule includes:

Gravity sewer and force main installation 12/2019 - 3/2020

Gravity sewer laterals 2/2020 - 3/2020

Force Main installation - 1/2020 - 3/2020

Final Paving estimated 5/2021

 

Balfour Lane Pumping Station:

Construction 02/2021 - 07/2021



Construction Area 7 (Perch Pond Road / Perch Pond Road Pumping Station)

PUMP STATION WORK (SEE BELOW)

Fall 2020 - Spring 2021

Construction for the installation of gravity sewer is tentatively planned to begin the week of 12/30/19 and continue through 1/24/20.  Gravity sewer lateral work is planned for the week of 1/20/2020 and continue through to 1/31/2020. Force Main/Low Pressure Sewer Installation will continue through 2/7/2020.

 

Sewer testing is expected to begin in this area 05/04/2020 and continue through to 05/22/2020.

 

Pump station work is estimated to begin the week of 05/18/2020 and continue intermittently through July 2021.

 

Pavement preparation for full width road reconstruction planned for 4/12/2021 with paving planned to follow on 4/13/2021.

 

Road work is expected to begin 10/28/2020 and continue through to 12/11/2020. Road work will include pavement preparation on Perch Pond Road/Jeanette Road areas.

 

Testing of the sewer main to be started the week of 1/18/2021 and continue intermittently through 2/26/2021.

 

 

Estimated Schedule includes:

Test Pits 9/2019

Gravity sewer and force main installation 12/2019 - 2/2020

Low pressure sewer installation 12/2019 - 2/2020

Gravity sewer and low pressure laterals 1/2020 - 2/2020

Final Paving estimated 4/12/2021 - 4/13/2021

 

Perch Pond Pumping Station:

Construction 04/2021 - 7/2021

Construction Area 8 (Heritage Lane)

Winter 2020 - Spring 2021

Construction for the installation of gravity sewer and service laterals is tentatively planned to begin the week of 3/16/2020 and continue through 5/08/2020. 

 

Testing of the sewer main to be started the week of 1/18/2021 and to continue through the week of 1/29/2021.

 

Staging of equipment and materials within the road right-of-way is likely for this area.

 

Sewer work and testing planned for the week of 4/05/2021 in this area.

 

Hydroseeding planned for this area the week on 6/7/2021.

 

Estimated Schedule includes:

Gravity sewer and installation 2/2020 - 5/2020

Gravity sewer laterals 2/2020 - 5/2020

Final Paving estimated TBD


Construction Area 9 (Sky Way and Ell Street / Sky Way Pumping Station)

PUMP STATION WORK (SEE BELOW)

Fall 2019 - Spring 2021 (Roadwork) / Fall 2019 - Spring 2021 (Pumping Station Work)

Construction is planned to continue through 12/13/19.

 

Sewer testing is planned to begin 4/06/2020 and continue through to 4/17/2020 in this area.

 

Pump station work is estimated to begin the week of 4/27/2020 and continue intermittently through July 2021.

 

Paving, roadway cleanup and site restoration planned for the weeks of 5/10/2021, 5/17/2021, and 5/24/2021.

 

Milling and pavement preparation is planned in this area beginning 5/03/2021.

 

Hydroseeding planned for this area the week on 6/7/2021.

 

Estimated Schedule includes:

Gravity sewer and force main installation continues 10/21 through 11/15

Gravity sewer laterals 11/18/19 - 12/13/19

Final Paving estimated 5/2021

 

Sky Way Pumping Station:

Construction 4/2020 - 07/2021

 

Construction Area 10 (White Pond Road)

Winter 2019 - Spring 2021

Low pressure sewer work is expected the week of 4/13/2020 and continuing through 4/24/2020.  Gravity sewer work is expected to begin the week of 6/15/2020 and continue through to 6/26/2020.

 

Staging of equipment and materials within the road right-of-way is likely for this area.

 

Sewer testing expected to begin in this area the week of 3/01/2021

 

Pavement preparation for full width paving planned for 4/12/2021 - 4/14/2021.

 

Paving planned in this area the week of 5/17/2021.

 

Estimated Schedule includes:

Gravity sewer and low pressure sewer installation 4/2020 - 6/2020

Gravity sewer and low pressure laterals 4/2020 - 6/2020

Final Paving estimated 4/2021 - 5/2021

 

Construction Area 11 (Lime Hill Road and Christopher Harding Lane)

Winter 2019 - Spring 2021

Work is planned to commence on 2/3/2020 and continue through 3/27/2020 for Gravity, Force Main, Low Pressure Sewer and Lateral Installation. 

 

Sewer testing is planned 4/19/2021 - 5/07/2021 in this area. Road preparation for paving is planned to begin the week of 4/19/2021. Road paving schedule to be determined the week of 4/26/2021.

 

Paving, roadway cleanup and site restoration planned for this area the week of 5/17/2021.

 

Hydroseeding planned for this area the week on 6/7/2021.

 

Estimated Schedule includes:

Test Pits to located existing utilities 12/2019

Gravity sewer and low pressure sewer installation 1/2020 - 4/2020

Gravity sewer and low pressure laterals 3/2020 - 4/2020

Final Paving estimated 4/2021 - 5/2021

 

Construction Area 12 (Vineyard Avenue, Waveland Avenue, Smith Street, Ellis Street, Bay View Street)

Winter/Spring 2020 - Spring 2021

Estimated Schedule includes:

Vineyard Ave:

 

Low pressure sewer work is estimated to begin the week of 3/23/2020 and continue through 4/03/2020. Gravity sewer work is expected to continue 5/25/2020 through to 6/05/2020.

 

Testing of the sewer main to be started the week of 4/12/2021.

 

Staging of equipment and materials within the road right-of-way is likely for this area.

 

Milling and pavement preparation is planned in this area beginning 5/03/2021.

 

Paving planned in this area on 5/06/2021.

 

Roadway cleanup and sewer manhole work the week of 5/10/2021.

 

Gravity sewer and low pressure sewer installation 3/2020 - 6/2020

Gravity sewer and low pressure laterals 3/2020 - 6/2020

Final Paving estimated 5/2021

 

Waveland Ave:

 

Gravity sewer work is expected to begin 5/11/2020 and continue through to 5/22/2020.

 

Sewer testing expected to begin the week of 3/22/2021.

 

Staging of equipment and materials within the road right-of-way is likely for this area.

 

Milling and pavement preparation is planned in this area beginning 5/03/2021.

 

Paving planned in this area on 5/06/2021 and the week of 5/10/2021. Roadway cleanup and site restoration planned the week of 5/17/2021.

 

Gravity sewer installation 5/2020 - 6/2020

Gravity sewer laterals 5/2020 - 6/2020

Final Paving estimated 5/2021

 

Smith Street:

 

Gravity sewer and service laterals work is expected to begin 4/20/2020 and continue through 6/05/2020.

 

Sewer testing expected to begin the week of 4/05/2021.

 

Road preparation for paving expected to begin the week of 4/19/2021 with paving estimated on 4/21/2021.

 

Sewer manhole work expected in this area the week of 5/10/2021.

 

Roadway cleanup and site restoration planned the week of 5/17/2021.

 

Staging of equipment and materials within the road right-of-way is likely for this area.

 

Gravity sewer installation 4/2020 - 5/2020

Gravity sewer laterals 4/2020 - 6/2020

Final Paving estimated 4/19/2021 - 4/23/2021

 

Ellis Street:

 

Low pressure sewer work is estimated to begin the week of 4/06/2020 and continue through 4/10/2020.  Gravity sewer work is estimated to begin 5/18/2020 and continue through to 5/29/2020.

 

Sewer testing expected to begin the week of 3/29/2021.

 

Paving planned in this area on 5/6/2021 and the week of 5/10/2021. Roadway cleanup and site restoration planned the week of 5/17/2021.

 

Staging of equipment and materials within the road right-of-way is likely for this area.

 

Gravity sewer and low pressure sewer installation 4/2020

Gravity sewer and low pressure laterals 4/2020 - 5/2020

Final Paving estimated 4/2021 - 5/2021

 

Bay View Street:

 

Low pressure sewer work is estimated to begin the week of 3/16/2020.

 

Gravity sewer and service laterals work is expected to begin the week of 5/04/2020 and continue through 5/29/2020.

 

Sewer testing planned for the weeks 4/5/2021 and 4/12/2021.

 

Road preparation for paving expected to begin the week of 4/19/2021 with paving estimated on 4/21/2021. Sewer testing tentatively scheduled for the week of 4/26/2021 in this area.

 

Sewer manhole work expected in this area the week of 5/10/2021.

 

Roadway cleanup and site restoration planned for the week of 5/17/2021.

 

Staging of equipment and materials within the road right-of-way is likely for this area.

 

Gravity sewer and low pressure sewer installation 3/2020 - 5/2020

Gravity sewer and low pressure laterals 4/2020 - 6/2020

Final Paving estimated 4/19/2021 - 4/23/2021

 

Construction Area 13 (Captain Richards Way)

Spring 2020 - Spring 2021

Low pressure sewer work is estimated to begin the week of 4/06/2020 and continue through 4/17/2020. Gravity sewer work is expected to begin the week of 6/01/2020 and continue through to 6/19/2020. Paving is planned for the week of 6/22/2020.

 

Paving planned for this area the week of 5/17/2021 with roadway cleanup and site restoration to follow.

 

Staging of equipment and materials within the road right-of-way is likely for this area.

 

Sewer testing expected to resume the week of 3/22/2021.

 

Estimated Schedule includes:

Gravity sewer and low pressure sewer installation 4/2020 - 6/2020

Gravity sewer and low pressure laterals 4/2020 - 6/2020

Final Paving estimated 4/2021 - 5/2021

 


Construction Area 14 (Linden Tree Lane)

Winter 2020 - Spring 2021

Work is planned to commence on 2/3/2020 and continue through 3/06/2020 for Gravity Sewer, Low Pressure Sewer Installation, and Service Laterals.

 

Sewer testing is planned to begin in this area 4/19/2021 - 4/23/2021. Preparation for full width road reconstruction expected the week of 5/03/2021, paving schedule to be determined.

 

Paving planned the week of 5/17/2021 with roadway cleanup and site restoration to follow during that week and into the week of 5/24/2021.

 

Hydroseeding planned for this area the week on 6/7/2021.

 

Estimated Schedule includes:

Gravity sewer and low pressure sewer installation 2/2020 - 3/2020

Gravity sewer and low pressure laterals 2/2020 - 3/2020

Final Paving estimated TBD

Construction Area 15 (Snow Lane)

Fall 2020 - Spring 2021

 

Estimated Schedule includes:

Water main work 2/2021 - 3/2021

Gravity sewer and low pressure sewer installation 2/2021 - 4/2021

Gravity sewer and low pressure laterals 2/2021 - 4/2021

Full width binder paving on 4/02/2021; final paving TBD in fall 2021.

Sewer work and sewer lateral work to continue through 4/2/2021. Paving, miscellaneous road work, and clean up is expected the week of 4/5/2021. Please note paving will not occur until sewer installation is complete on this roadway.

Sewer testing scheduled on this road the week of 5/03/2021 and 5/10/2021. Sewer manhole work is also expected in this area during the week of 5/10/2021.

 

Construction Area 16 (Uncle Alberts Drive)

Fall 2019 - Spring 2021

 

Estimated Schedule includes:

Low pressure sewer installation for 10/2019 - 11/2019

Low pressure laterals 11/2019 - 12/2019

Final Paving estimated for 4/2021 - 5/2021

Sewer testing expected to begin in this area the weeks of 4/12/2021 and 4/19/2021

Paving planned the week of 5/17/2021 with roadway cleanup and site restoration to follow the week of 5/24/2021.

Hydroseeding planned for this area the week on 6/7/2021.

 

 
Construction Area 17 (All Roads) 1D-1  
 Fall 2019

 Construction has concluded for all roads under this project including:

  • Meetinghouse Road, Old Queen Anne Road, Middle Road, Duncan Lane, Partridge Path, Mallard Road, and Sam Ryder Road

 

Construction Area 18 (Meetinghouse Road) 1D-1

EXPECT DELAYS

 Fall 2019 - Winter 2020

Pumping Station No. 6 at 601 Meetinghouse Road

Road will remain open. Possible alternating traffic for select times.

  • Currently under construction, delays may occur on Meetinghouse Road as materials are delivered to site.

 

 
Construction Area 19 (Stony Hill Road)
 Winter 2021 - Summer 2021

 Gravity Sewer Installation:

  • Construction has completed

 

 Low Pressure Sewer Installation:

  • Construction has completed

 

 Stormwater Installation:

  • Currently under construction

 

 Testing and Final Paving:

  • Testing has completed.
  • Final Paving anticipated Summer 2021.

 

 

Construction Area 20 (Crowell Road/Lake Street)

EXPECT DELAYS

 Winter 2021 - Summer 2021

Active detour routing Crowell Road thru traffic to Tip Cart Drive to Barcliff Ave to Bell Road to return to Stony Hill Road

 Stormwater Installation:

  • Currently under construction

 

 Watermain Work:

  • Currently under construction

 

 Gas Main Work:

  • Construction has concluded.

 

 Testing and Final Paving:

  • Anticipated construction Summer 2021.

 

 

Construction Area 21 (George Ryder Road South & Market Place)
 Fall 2020 - Winter 2021

 Estimated Schedule includes:

  • Gravity sewer installation: Construction has concluded
  • Sewer Testing: Construction has concluded
  • Final Paving: TBD

 

 

Construction Area 22 (Hardings Lane)

 Fall 2020 - Winter 2021

 Estimated Schedule includes:

  • Low pressure sewer installation: Construction has completed
  • Sewer Testing: Construction has concluded
  • Final Paving: Anticipated end of July 2021

 

 

 