Town of Chatham Collection System Construction Project
Welcome Areas of Work Public Notices Schedule Information Contact
Links
Town of Chatham Website
Frequently Asked Questions (FAQ)
Comprehensive Management Plan
Chatham Water & Sewer
Chatham DPW
Chatham Natural Resources
Town of Chatham Website
Chatham Maps Online
Chatham Businesses

Areas of Work Map
Areas of Work Map - Phase 1D-1
Click here to enlarge the map above.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Areas of Work Map - Phase 1C-3&4

Click here to enlarge the map above.

 

 

 

 

 

 

 

 

 

Areas of Work

Contracts: (click below for street listing)

Phase 1D-1 (Contract 2018-CWMP-4) - Chatham - Harwich Regionalization Connection Project

Phase 1C-3&4 (Contract 2018-CWMP-2) - Oyster Pond Sewer Extension

 

 

Phase 1D-1

Gravity and Pressure Sewer Areas

As sewer installation is completed, contractor will be installing lateral services and following this work these areas may still require site restoration and cleanup.

  • Old Queen Anne (OQA) Road (closest to Harwich and Meetinghouse Road)
  • Meetinghouse Road (from OQA to Middle Road)
  • Middle Road (from Meetinghouse to WPCF back entrance)
  • Duncan Lane
  • Mallard Road
  • Partridge Path
  • Paulding Drive (entrance)
  • Mill Hill Road (entrance)
  • Tanglewood (entrance)
  • Unnamed Way (1549 & 1551 OQA)
  • Cemetary Road (Harwich) -connection
  • Herdon Road (Harwich) - connection
  • Chickadee Lane (Harwich) - connection
  • Church Street (Harwich) -connection
  • Sam Ryder Road (between WPCF Drive and Rt 28)

 

Water Main Work

In addition, water main work will occur on portions of the following roads:

  • Duncan Lane

This work will include installation of new water main and connection of water services.

Temporary water services may be required on other street depending on utility conflicts.  In addition there may be water service replacements made on other roads not listed under water main work, but identified for sewer work to replace old steel services.

Stormwater Improvements

As part of the Town's sewer infrastructure projects, the Town is also installing new stormwater systems in the following areas:

  • Meetinghouse Road

Phase 1C-3&4

Gravity and Pressure Sewer Areas

As sewer installation is completed, contractor will be installing lateral services and following this work these areas may still require site restoration and cleanup.

  • Ethelma Drive
  • Barbara Drive
  • Cynthia Drive
  • Wilfred Road
  • Balfour Lane
  • Sky Way
  • Ell Street
  • White Pond Road
  • Waveland Avenue
  • Captain Richards Way
  • Ellis Street
  • Bay View Street
  • Carolyn Drive
  • Jeanette Drive
  • Jeanette Road
  • Perch Pond Road
  • Heritage Lane
  • Linden Tree Lane
  • Snow Lane
  • Lime Hill Road
  • Christopher Hardings Lane
  • Uncle Alberts Drive
  • Smith Street
  • Vineyard Avene

 

Water Main Work

In addition, water main work may occur on portions of the following roads:

  • Wilfred Road
  • Snow Lane
  • Captain Richards

This work will include removal and installation of new water main and reconnection of water services.  Temporary water services may be required depending on utility conflicts.  In addition there may be water service replacements made on other roads not listed under water main work, but identified for sewer work to replace old steel services.

Gas Utilities

National Grid is currently working on natural gas main work in Town various locations.

 